Replaced Damaged Promethean ActivPanel with new 65inch Nickel ActivPanel. Tested new ActivPanel and Confirmed working with no issues. Placed new DSI Asset Tag on Panel. Removed Old Asset Tag from Damaged Panel and Placed on Document Provided by GDOE. Brought Damaged Promethean ActivPanel to DSI Office for Stripping of Parts for Spare.
|
|
Work Completed |
Technician |
Check-in |
Check-out |
Actual Hrs |
|
|
1 |
Replaced Damaged Promethean ActivPanel with new 65inch Nickel ActivPanel. Tested new ActivPanel and Confirmed working with no issues. Placed new DSI Asset Tag on Panel. Removed Old Asset Tag from Damaged Panel and Placed on Document Provided by GDOE. Brought Damaged Promethean ActivPanel to DSI Office for Stripping of Parts for Spare. |
Charles Rafanan
|
05/27/2022 10:45 am |
05/27/2022 11:45 am |
01:00
|