- Removed Doors 118, 129A and 141 that was routed through AC42 to AC62. Removed the defective AC42 after.
- Mounted the replacement AC42. Wired its doors back in. Switched the Door 100A from the backup AC12 to the new AC42.
- Tested each reconnected doors, Verified all devices work properly.
- Walked through the process of turning over the access and credentials with Monica.
- Deleted DSI account off their verkada command. Transferred 2FA/MFA to Monica, verified her SMS.
- Monica signed turnover form.
|
|
Work Completed |
Technician |
Check-in |
Check-out |
Actual Hrs |
|
|
1 |
- Removed Doors 118, 129A and 141 that was routed through AC42 to AC62. Removed the defective AC42 after.
- Mounted the replacement AC42. Wired its doors back in. Switched the Door 100A from the backup AC12 to the new AC42.
- Tested each reconnected doors, Verified all devices work properly.
- Walked through the process of turning over the access and credentials with Monica.
- Deleted DSI account off their verkada command. Transferred 2FA/MFA to Monica, verified her SMS.
- Monica signed turnover form. |
Sean Bacani
|
05/22/2026 01:20 pm |
05/22/2026 04:30 pm |
03:10
|